Manage Dependencies
Participate with relevant stakeholders to identify, negotiate, and
track critical dependencies.
- Conduct reviews with relevant stakeholders.
- Identify each critical dependency.
- Establish need dates and plan dates for each critical dependency
based on the project schedule.
- Review and get agreement on the commitments to address each
critical dependency with the people responsible for providing the
work product and the people receiving the work product.
- Document the critical dependencies and commitments. Documentation of commitments typically includes:
- Describing the commitment
- Identifying who made the commitment
- Identifying who is responsible for satisfying the commitment
- Specifying when the commitment will be satisfied
- Specifying the criteria for determining if the commitment has been satisfied
- Track the critical dependencies and commitments and take
corrective action as appropriate. Tracking the critical dependencies typically includes:
- Evaluating the effects of late and early completion for impacts on future activities and milestones
- Resolving actual and potential problems with the responsible people where possible
- Escalating to the appropriate managers the actual and potential problems not resolvable with the responsible people